Kerr Field Project

A groundbreaking ceremony was held on February 7th. The renovation of Kerr Field has begun!

The William Penn School District is in Phase 1 of our Ten-Year Facilities Improvement Plan which includes the Kerr Field project. Planned upgrades to this facility will allow Kerr Field to be an improved stadium for student and community use.

 

Project Milestones
Feb. 17, 2023 Permits and Approvals (see note below)
Feb. 20, 2023 Commence site mobilization and demolition
Feb. 27, 2023 Commence site earthwork
Mar. 13, 2023 Commence Site utility installation
Mar. 13, 2023 Commence building construction
Aug. 15, 2023 Synthetic Turf completion (pending issuance of permit and weather)
Oct. 15, 2023 Synthetic Track Surfacing completion (includes 28-day asphalt cure period)
(pending issuance of permit and weather)

 



 

Local Contractors

Steel – Allen’s Iron Works – Yeadon
Trademark Plumbing – Lansdowne
Plumbing – GM Mechanical – Aldan
Roofing – Ipina Roofing – East Lansdowne
Manny Roofing – Upper Darby
Masonry Setag Construction – Colwyn
Demo and cleanup – Lees Hauling – Darby
Cavalier Fence & Iron Shop – Darby (iron work only)
Accurate Recycling – Lansdowne
Blessing Electric – Lansdowne
Complete Electric Corp – Darby
MC Electric – Upper Darby

NOTE: The above contractors will be invited to present a proposal for portions of the project at the appropriate time.

 

Kerr Field Progress Photos

Groundbreaking Ceremony - February 7, 2023