WPSD celebrated the opening of the Rap Curry Athletic Complex Kerr Field on November 16, 2023.
Project Milestones |
|
| Feb. 17, 2023 | Permits and Approvals (see note below) |
| Feb. 20, 2023 | Commence site mobilization and demolition |
| Feb. 27, 2023 | Commence site earthwork |
| Mar. 13, 2023 | Commence Site utility installation |
| Mar. 13, 2023 | Commence building construction |
| Aug. 15, 2023 | Synthetic Turf completion (pending issuance of permit and weather) |
| Oct. 15, 2023 | Synthetic Track Surfacing completion (includes 28-day asphalt cure period) (pending issuance of permit and weather) |
Local Contractors
Steel – Allen’s Iron Works – Yeadon
Trademark Plumbing – Lansdowne
Plumbing – GM Mechanical – Aldan
Roofing – Ipina Roofing – East Lansdowne
Manny Roofing – Upper Darby
Masonry Setag Construction – Colwyn
Demo and cleanup – Lees Hauling – Darby
Cavalier Fence & Iron Shop – Darby (iron work only)
Accurate Recycling – Lansdowne
Blessing Electric – Lansdowne
Complete Electric Corp – Darby
MC Electric – Upper Darby
NOTE: The above contractors will be invited to present a proposal for portions of the project at the appropriate time.
Kerr Field Progress Photos
Groundbreaking Ceremony - February 7, 2023